Annexure - III

(Chapter-VI)

The status of ongoing projects costing Rs 20.00 Crores and above as on December’99 is given below:

Com-pany

Name of

Project

Capacity

Govt. Approval

Comm. Date

Anti. Comm. Date

Time Overrun (Months)

Sanc. Cost (Rs.Crs.)

Anti. Cost

(Rs.Crs.)

(as per AP2000-01

Exp. Upto Mar.’99

(Rs.Crs.)

BE/ RE

99-2000

(Rs.Crs.)

Exp.

Apr.’99 to Dec’99

( Rs.Crs.)

Prov.

Remarks

NLC

Expansion of Mine-I

4 MT

(6.5 mt to 10.5 mt)

03/92

$10/96

(05/1999)

$9/2000

(11/2002)

42

1336.93

1602.94

(08/99 base)

683.66

304.35

304.35

262.43

Erection of BWEs and Spreader commenced in Jun.’98 and Oct.’98 respectively and is in progress.

NLC

TPS-I Expansion

2 x 210 MW

02/96

02/2001

05/2002

15

1590.58

1520.99

(08/99 base)

105.08

250.60

243.99

51.48

Orders for all major packages have been issued except AHS. For Main Plant Package Boiler erection works commenced on 30.6.99 and works are in progress.

NLC

Mine-IA

3 MTPA

02/98

$ 02/2001

(2002-03)

$ 07/2001

(2002-03)

5

1032.81

1063.18

(08/99 base)

21.80

165.00

157.92

21.97

EMP clearance was issued by MOE &F on 01.03.99 and conditions in LOA were revoked on the same day itself. Supplies expected from Jan’2000.

Figures within brackets refers to attaining full capacity production stage. $ -- System commissioning