Annexure - III
(Chapter-VI)
The status of ongoing projects costing Rs 20.00 Crores and above as on December99 is given below:
Com-pany |
Name of Project |
Capacity |
Govt. Approval |
Comm. Date |
Anti. Comm. Date |
Time Overrun (Months) |
Sanc. Cost (Rs.Crs.) |
Anti. Cost (Rs.Crs.) (as per AP2000-01 |
Exp. Upto Mar.99 (Rs.Crs.) |
BE/ RE 99-2000 (Rs.Crs.) |
Exp. Apr.99 to Dec99 ( Rs.Crs.) Prov. |
Remarks |
NLC |
Expansion of Mine-I |
4 MT (6.5 mt to 10.5 mt) |
03/92 |
$10/96 (05/1999) |
$9/2000 (11/2002) |
42 |
1336.93 |
1602.94 (08/99 base) |
683.66 |
304.35 304.35 |
262.43 |
Erection of BWEs and Spreader commenced in Jun.98 and Oct.98 respectively and is in progress. |
NLC |
TPS-I Expansion |
2 x 210 MW |
02/96 |
02/2001 |
05/2002 |
15 |
1590.58 |
1520.99 (08/99 base) |
105.08 |
250.60 243.99 |
51.48 |
Orders for all major packages have been issued except AHS. For Main Plant Package Boiler erection works commenced on 30.6.99 and works are in progress. |
NLC |
Mine-IA |
3 MTPA |
02/98 |
$ 02/2001 (2002-03) |
$ 07/2001 (2002-03) |
5 |
1032.81 |
1063.18 (08/99 base) |
21.80 |
165.00 157.92 |
21.97 |
EMP clearance was issued by MOE &F on 01.03.99 and conditions in LOA were revoked on the same day itself. Supplies expected from Jan2000. |
Figures within brackets refers to attaining full capacity production stage. $ -- System commissioning