CHAPTER-VI
Coal Projects and Land Management
Projects sanctioned during 1999-2000
Mining Projects
| Company | Costing |
|||||
More than Rs.100crs. (No.) |
Rs.20-100 crs. (No.) |
Rs.2-20 crs. (No.) |
Total (No.) |
Sanctioned Cost (Rs. crs.) |
Ultimate Capacity (mty) |
|
| ECL | 6 | 6 | 44 | 56 | 3,389.69 | 40.12 |
| BCCL | 3 | 7 | 57 | 67 | 1,546.98 | 30.70 |
| CCL | 5 | 14 | 48 | 67 | 2,695.79 | 57.20 |
| NCL | 7 | 1 | 3 | 11 | 4,621.83 | 50.10 |
| WCL | 1 | 28 | 60 | 89 | 2,298.31 | 42.40 |
| SECL | 3 | 30 | 57 | 90 | 2,793.56 | 65.53 |
| MCL | 7 | 5 | 9 | 21 | 1,710.60 | 43.36 |
| CIL | 32 | 91 | 278 | 401 | 19,056.76 | 329.41 |
| SCCL | 9 | 15 | 49 | 73 | 4,902.38 | 39.695 |
6.4 As on 31.12.1999, out of total 401 mining projects of CIL, each costing Rs.2.0 crores and above, 278 projects stand completed (including projects where coal reserve have since exhausted). Out of remaining 103 projects under various stages of implementation, 47 are on schedule and 56 are delayed. In SCCL, out of total 73 mining projects, 50 projects have been completed. Out of the remaining 23 projects, 6 are on schedule and 17 are delayed. The company-wise position is as under
Total No. of completed/on-going projects
| Company | Total No. of Projects |
No. of Completed Project |
On-going Projects |
Projects under implementation | |
On Schedule |
Delayed |
||||
| ECL | 56 | 40 | 16 | 9 | 7 |
| BCCL | 67 | 56 | 11 | 2 | 9 |
| CCL | 67 | 44 | 23 | 3 | 20 |
| NCL | 11 | 9 | 2 | 1 | 1 |
| WCL | 89 | 67 | 22 | 12 | 10 |
| SECL | 90 | 65 | 25 | 17 | 8 |
| MCL | 21 | 17 | 4 | 3 | 1 |
| CIL | 401 | 298 | 103 | 47 | 56 |
| SCCL | 73 | 50 | 23 | 6 | 17 |
6.5 Non-mining Projects
| Company | Over Rs.100 crs. (No.) |
Rs.20-100 crs. (No.) |
Rs.2-20 crs. (No.) |
Total (No.) |
Sanctioned Cost (Rs. crs.) |
| ECL | 0 |
1 | 23 | 24 | 220.60 |
| BCCL | 1 |
5 | 62 | 68 | 1,036.92 |
| CCL | 1 |
3 | 29 | 33 | 533.79 |
| NCL | 0 |
5 | 10 | 15 | 387.86 |
| WCL | 0 |
2 | 19 | 21 | 201.75 |
| SECL | 1 |
0 | 42 | 43 | 430.11 |
| MCL | 0 |
2 | 18 | 20 | 319.73 |
| CIL (Total) | 3 |
18 | 203 | 224 | 3,130.76 |
| SCCL | - |
1 | 7 | 8 | 97.63 |
Note: Dankuni Coal Complex is shown against SECL.
At the Govt. level projects, each costing Rs.20.0 crores and above, are being monitored. As on 31.12.1999, there were 67 such projects under implementation in Coal India Ltd. (CIL) and Singareni Collieries Company Ltd. (SCCL). Summarised position of these on-going projects is as follows (at Table-A below)
Details of projects, company-wise costing Rs.20.0 crores and above in the Coal and Lignite Sector as on 31.12.1999 are given in Annexure-III.
6.8 Steps Taken To Improve Project Implementation
Regular follow up meetings with the representatives of the public sector mining equipment manufactures through measures like:
Sophisticated geological and geophysical exploration techniques adopted for advance forecasting of geo-mining conditions:
Table-A
Company |
No. of Projects |
Sanctioned Capital (Rs.crs.) |
Production Capacity (mty) |
Projects on Schedule |
Projects Delayed |
CIL |
58 |
7,817.37 |
83.5 |
32 |
26 |
SCCL |
9 |
1,111.25 |
6.65 |
6 |
3 |
Total |
67 |
8,928.62 |
90.15 |
38 |
29 |
e) Constitution of a Committee of Group of Ministers (GOM) :
GOM constituted under the directive of the PM to recommend specific suggestions to cut delays in implementation of projects ahas since submitted its report. Main recommendations are identification of projects in view of resource constraints. CIL is taking action accordingly.
f.) Guidelines by the Govt. on specific measures to cut delays in implementation of projects
A Group of Ministers (GOM) was constituted under the directive of the PM in February, 1994 to suggest specific measures to cut delays in implementation of projects The Group submitted its report. Main recommendations were identification of projects for shelving or transferring to Joint/Private sector and reprioritisation of projects in view of resource constraints. The Govt. has accepted these recommendations. Department of Programme Implementation is co-ordinating with all the concerned Ministries in regard to implementation of these decisions. On the advice of the Department, Coal companies are taking necessary action in this regard.
6.9 Assistance Required in Project Implementation:
LIGNITE SECTOR:
PROJECTS SANCTIONED:
6.10 No new major projects have been sanctioned. However, Advance Action proposals for the following projects have been approved in March '99 for incorporating expenditure on preliminary activities.
1. Second Mine Expansion from 10.5 MT to 14.5 MT of lignite per annum.
2.Second T.P.S expansion by adding 1 unit of 500 MW raising the capacity from 1470 MW to 1970 MW.
3. III Mine - 12 MT of Lignite per annum.
4. III T.P.S - 3 x 500 MW capacity.
6.11 Details of projects costing Rs. 20 crores and above in respect of NLC as on 31.12.99 is given in Annexure III .